Invensys Rail commissions Malaysian double tracking

Listen to this article

Invensys Rail has delivered the first critical phase of the Seremban to Gemas Double Tracking Project in time for planned commencement of the suburban passenger service to Sungai Gadut.

The project forms part of the Malaysian Government’s RM3.45 billion Seremban-Gemas double tracking and electrification project due for completion in December 2012.

Phase I included modification and extension of Seremban station, a new station and interlocking at Sungai Gadut and a 10km block section between stations which includes the halt of Senawang.

Despite a significant flash flooding occurrence in January 2011, Invensys Rail teams from Bangalore, Indonesia, Malaysia and Thailand rallied together with IRCON to commission the project on time.

Invensys Rail’s Regional Manager, Owen Clenick said:

“The dedication and tenacity of our international teams to deliver the project on time was second to none and shows the lengths that Invensys Rail will go to deliver on time for its customer”.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Latest Rail News

GB Railfreight extends haulage contract with Network Rail

GB Railfreight (GBRf) one of the country’s largest rail freight operators has extended its haulage contract with Network Rail,...

More like this...