Plumstead preparation complete

Listen to this article

Preparatory work at Crossrail’s Plumstead portal is now complete. Engineers from Hochtief Murphy JV worked safely just three metres from the main line.

The Plumstead portal will take Crossrail’s slurry tunnel boring machines below the River Thames in August. The last diaphragm wall panel marked the end of six months of intensive ground engineering utilising varying methods of piling, diaphragm walling and grouting. The works have seen 2,300t of reinforcement fixed on site and 22,000m3 of structural concrete poured using five rigs at peak activity with a combined workforce of 70 from Skanska Cementation and HMJV.

The greatest achievement has been the completion of the works within 3 metres of the North Kent running line with up to 16 train movements per hour. The close working relationship with Network Rail was a key factor in ensuring the success of the works and has set a new benchmark for the installation of large scale ground engineering in close proximity to live railway infrastructure.

The next phase of works will involve bulk excavation of the portal and propping works in preparation for the arrival of the tunnel boring machines later this year.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Latest Rail News

Network Rail engineers gear up for £135m investment in Britain’s railway this May

More than 800 projects* will take place across Britain’s railway this coming early and late May bank holidays, designed...

More like this...